Panthers host rookie minicamp | Charlotte, N.C. sports news

May 10, 2025

SAISD program coordinator had summer school items delivered to his home, invoices show

May 10, 2025

Where will failed ’70s Soviet probe land after it crashes back to Earth? Nobody knows

May 10, 2025
Facebook X (Twitter) Instagram
This Week’s News – Local News from 21 Major U.S. CitiesThis Week’s News – Local News from 21 Major U.S. Cities
  • Home
  • Austin
  • Boston
    • Charlotte
    • Chicago
  • Columbus
  • Dallas
    • Denver
    • Fort Worth
  • Houston
    • Indianapolis
    • Jacksonville
  • Los Angeles
  • New York
    • Philadelphia
    • Phoenix
  • San Francisco
    • San Antonio
    • San Diego
  • Washington
    • San Jose
    • Seattle
This Week’s News – Local News from 21 Major U.S. CitiesThis Week’s News – Local News from 21 Major U.S. Cities
Home » Documenters: Downtown pedestrian and signal improvements proceed, with pause for World Cup
Fort Worth

Documenters: Downtown pedestrian and signal improvements proceed, with pause for World Cup

Anonymous AuthorBy Anonymous AuthorMay 9, 2025No Comments5 Mins Read
Share Facebook Twitter Pinterest LinkedIn Tumblr Telegram Email Copy Link
Follow Us
Google News Flipboard
Share
Facebook Twitter LinkedIn Pinterest Email


Fort Worth is moving forward with its program to update pedestrian ramps and traffic signals downtown, with the project to proceed in two phases and paused to allow for play of the FIFA World Cup 26 games in DFW. — Brian Farda

Documenter name: Brian Farda

Agency: Fort Worth Public Meetings

Date: April 24, 2025

See more about this meeting at Documenters.org

Documenters

Documenters empowers people like you to help fill the gaps in reporting on Tarrant County public meetings. Find out how you can join here.

Notes

Fort Worth is planning upgrades to seven intersections (1st to 9th streets, but not 3rd or 4th) and enhancements for pedestrian safety along Main Street. City officials held a public Main Street Downtown Intersection Project meeting April 24, 2025, in the City Center board room downtown. The meeting began at 11 a.m. It was held in an open-house format with a short presentation at the beginning.

Present at the meeting were representatives from:

City of Fort Worth Transportation & Public Works

Lauren Prieur (TPW director)

Lara Ingram (TPW Communications, public information officer)

City of Fort Worth District 9

Mia Boatner (district director)

Bartlett & West engineering firm

Todd Milburn, design engineer

Brandon Johnson, lead designer

Project manager

Seth Cooksey opened the meeting with greetings, introductions and contact information. He then gave a presentation that included:

Project scopeTo upgrade the signalized intersections by installing powder-coated black poles, arms, pedestrian traffic signals, pan-tilt-zoom cameras, signage and ADA ramps on Main Street from 1st to 9th streets, except at 3rd and 4th streets; to construct power pedestals on 8th, 9th and Weatherford streets; to add signal battery backups to power pedestals at 3rd, 4th, 8th, 9th and Weatherford streets.

Project phasesPhase I will consist of updating traffic signals and improving sidewalk curb ramps at 1st and 2nd streets. Then, a new power pedestal and battery backup will be added at Weatherford and Main streets. Finally, a new battery backup will be added to existing power pedestals at 3rd and 4th streets.

Phase II will consist of updating traffic signals and improving sidewalk curb ramps at 9th, 8th, 7th, 6th and 5th streets. Then, a new power pedestal and battery backup will be added at 8th and 9th streets.

Why this project?The Main Street Downtown Intersection Project was funded by a 2022 Bond Program and is intended to upgrade pedestrian and vehicle traffic infrastructure to address the high number of pedestrian injuries along this major downtown thoroughfare.

The project addresses the aging signal infrastructure and custom-made parts no longer available. Moreover, Main Street has limited capability to run energy efficient signals during power outages.

The project proposes upgrades to meet current industry standards and overall safety improvements for all users. This also will include updates to the aesthetics of the signal system to match 3rd and 4th streets as well as improved pedestrian access elements such as ADA compliant curb ramps. 

Project statusThe project is in its final submittal phase, which is due May 2025. This includes final plans, specifications and a final estimate.

Final designsConcept boards included the final design signals and sidewalk ramp visual renderings for each intersection. Additional photos showed the 3rd and 4th streets completed upgrades that will be extrapolated to the other intersections.

Improved access and traffic controlsContractors will be required to stage construction and sidewalk closures to maintain pedestrian access to all businesses and entrances. Contractors may also set up temporary street crossings to maintain pedestrian side street access.

Cooksey frequently noted that the Main Street Downtown Intersection Project is simply a continuation of infrastructure improvements that are already underway and in place at the 3rd Street and 4th Street intersections.

Todd Milburn took over the presentation shortly to cover the issue of pedestrian access to businesses along Main Street while these improvements are underway. He pledged to coordinate with and liaise between property owners and contractors in order to minimize any disruptions to nearby business operations. A key component of this will be prioritizing pedestrian access to businesses while construction is ongoing.

Cooksey continued his presentation and discussed the following:

Project schedule Currently completing the design phase

 Contract execution for Phase I construction — spring 2025

 Contract execution for Phase II construction — spring 2026

 Estimated construction start for Phase I — summer 2025

 Estimated construction start for Phase II — summer 2026

 Estimated construction duration for Phase I — Five months

 Estimated construction duration for Phase II — Eight months

 Estimated total construction cost — around $2.6 million

FIFA World Cup 26 pauseThe World Cup event has been worked into the construction schedule to allow for the increased visitor traffic that is anticipated and the subsequent need for easy pedestrian access to businesses.

Cooksey then made some closing remarks, thanked attendees and opened the floor for questions. The Q&A session was brief and centered around possible disruptions to nearby businesses:

How long does it take to complete each corner? (Up to three weeks per corner.)

How long does it take to complete each intersection? (One to two months per intersection.)

Lastly, Cooksey noted that his project slide deck will be posted soon to the Fort Worth Main Street Downtown Intersections website.

There were approximately 25 attendees and presenters.

If you believe anything in these notes is inaccurate, please email us at [email protected] with “Correction Request” in the subject line.

Related

Fort Worth Report is certified by the Journalism Trust Initiative for adhering to standards for ethical journalism.

Republish This Story

Creative Commons License

Republishing is free for noncommercial entities. Commercial entities are prohibited without a licensing agreement. Contact us for details.



Source link

Share. Facebook Twitter Pinterest LinkedIn Tumblr Email
Anonymous Author
  • Website

Related Posts

Mercy Culture Church breaks ground on shelter for human trafficking victims, with plans for more

May 9, 2025

Documenter of the Week: Brian Farda

May 9, 2025

Documenters: Year-end awards at Everman ISD

May 9, 2025
Add A Comment
Leave A Reply Cancel Reply

News

Panthers host rookie minicamp | Charlotte, N.C. sports news

By Anonymous AuthorMay 10, 2025

Rookies, headlined by Tetairoa McMillan, took the practice field for the first time. CHARLOTTE, N.C.…

‘We need people’: Asheville resort serves as symbol of western NC resilience

May 10, 2025

Expert weighs in on the selection of Pope Leo XIV

May 10, 2025
Top Trending

Where will failed ’70s Soviet probe land after it crashes back to Earth? Nobody knows

By Anonymous AuthorMay 10, 2025

A Soviet spacecraft launched more than 50 years ago on a failed…

Mass. weather: Up to 2 inches of rain possible until Saturday, flood risk continues

By Anonymous AuthorMay 10, 2025

Rain is expected to continue falling into Friday night and into the…

Springfield Armory awaits return of rare rifle stolen decades ago

By Anonymous AuthorMay 10, 2025

SPRINGFIELD — The Springfield Armory Historic Site will host an exhibition of…

Subscribe to News

Subscribe to our newsletter and never miss our latest news

Subscribe my Newsletter for New Posts & tips Let's stay updated

Welcome to ThisWeeksNews.com — your go-to source for the latest local news, community updates, and insightful stories from America’s most vibrant cities.

We cover real stories that matter to real people — from breaking headlines to neighborhood highlights, business trends, cultural happenings, and public issues. Our mission is to keep you informed, connected, and engaged with what’s happening around you.

Subscribe to Updates

Subscribe to our newsletter and never miss our latest news

Subscribe my Newsletter for New Posts & tips Let's stay updated

Facebook X (Twitter) Instagram Pinterest
  • Home
  • About Us
  • Advertise With Us
  • Contact Us
  • DMCA
  • Privacy Policy
  • Terms & Conditions
© 2025 thisweeksnews. Designed by thisweeksnews.

Type above and press Enter to search. Press Esc to cancel.